Show Me the Money? When a Sum Approximate Counts as a Sum Certain
Client Alert | 2 min read | 03.22.21
In Creative Management Services, LLC, dba MC-2 v. U.S. (Feb. 26, 2021), the Federal Circuit affirmed a Court of Federal Claims decision dismissing a contractor’s appeal of the government’s Contract Disputes Act (CDA) claim as untimely, holding that the contractor appealed more than 12 months after receiving a contracting officer’s (CO) final decision. On appeal, the contractor alleged that the final decision was not a valid claim because it did not state a “sum certain” as required by the CDA, and this deficiency meant that the 12-month appeal period had not started to run.
The contractor was awarded a General Services Administration (GSA) task order to provide marketing and logistical support for an annual GSA conference, and was required to keep the revenue it collected for the conference in a trust account. When GSA canceled the conference in the fourth year and asked the contractor to return all remaining money in the trust account, the contractor refused and submitted a termination for convenience proposal to GSA. GSA subsequently issued two letters to the contractor demanding an accounting of the trust account and all money that remained in it. The CO then issued a final decision on the contractor’s termination proposal and on GSA’s claim to the remaining funds in the trust account, without providing a dollar amount. The contractor filed suit three years after the final decision was issued, challenging the government’s claim to the trust account funds.
The Federal Circuit agreed with the Court of Federal Claims that the CO’s final decision was valid and provided the contractor with adequate notice of the government’s claim, thus starting the statute of limitations clock. Notably, the Court held that a CDA claim need not identify a “precise” monetary amount, and that there is no “rule” that qualifying terms such as “nearly” or “approximately” cannot be a sum certain as long as the amount is readily ascertainable. Here, despite GSA’s use of the term “approximately” to describe its claimed amount from the trust account, the contractor knew (or could easily ascertain) the balance of the trust account and knew the value of its termination settlement costs, and could therefore calculate the amount owed to the government. This decision is a good reminder regarding the importance of timely appealing final decisions.
Contacts
Insights
Client Alert | 4 min read | 06.25.26
Twin Executive Orders Seek to Spur Quantum Leap in Technology and Cybersecurity
On June 22, 2026, President Trump signed two executive orders, “Securing the Nation Against Advanced Cryptographic Attacks” (Quantum Security EO) and “Ushering in the Next Frontier of Quantum Innovation” (Quantum Innovation EO), marking the most significant federal action on quantum technology since the Quantum Computing Cybersecurity Preparedness Act of 2022, which directed agencies to harden their information systems against quantum-enabled hacking. The orders seek to speed the development of quantum computers, which are advanced processors that can calculate multiple possibilities simultaneously and thus solve problems exponentially faster than traditional computers. At the same time, the orders look to protect against the danger that quantum technology can “break” traditional encryption by easily decoding it. Of particular note for government contractors, the Quantum Security EO directs agencies to update federal acquisition regulations to require contractors by 2031 to adopt information processing standards that resist quantum-enabled codebreaking.
Client Alert | 7 min read | 06.24.26
Client Alert | 3 min read | 06.24.26
Client Alert | 4 min read | 06.23.26
EPA Hands Over AI Data Center Regulation to States and Communities to Develop Best Practices