COVID Costs Claim Succeeds: Contractor Entitled to Recover for Performance of Contract Despite Base Closure
Client Alert | 2 min read | 09.05.23
In StructSure Projects, Inc., ASBCA No. 62927, the Armed Services Board of Contract Appeals (Board) granted an appeal seeking recovery for increased costs resulting from the COVID-19 pandemic. The underlying task order involved design and alteration services for existing medical facilities at Travis Air Force Base, and included a specific Contract Line Item Number (CLIN) for the provision of temporary phasing facilities that the Government could use while the construction work was ongoing. When the pandemic began in March 2020, StructSure and its subcontractors had to stop their on-site construction work for 44 days because the Government had limited base access for contractors deemed to be not mission-essential. StructSure later sought schedule and monetary relief, but the Government only granted schedule extensions under the Default clause.
StructSure eventually submitted a monetary claim for the additional costs associated with renting furniture and equipment for the temporary phasing facilities because the schedule extensions meant that it would continue to incur cost beyond the original period of performance. Although the Government had continued to use the facilities during the stop-work period, the Government denied the claim on the basis that the base closure was a sovereign act rather than a change, and also because the Coronavirus, Aid, Relief, and Economic Security Act (“CARES Act”) was not intended to provide this type of relief on a fixed-price task order.
On appeal before the Board, the Government again raised the sovereign acts defense. Neither party disputed that the base closure was a “public and general sovereign act,” and the Board agreed that the closure delayed completion of the construction activity. However, the Board found that the sovereign acts doctrine did not apply, because the COVID restriction did not prevent StructSure from delivering the temporary phasing facilities. The Board found that StructSure was entitled to compensation because StructSure delivered, and the Government utilized, the temporary facilities during the delay period and during the extension granted due to the COVID delay.
This decision is a significant reminder that, even where a sovereign act is involved, contractors still may be entitled to recover for certain increased costs of performance. Contractors should examine the circumstances and impacts carefully to ensure that they request equitable adjustments to the contract price where appropriate.
Contacts
Insights
Client Alert | 5 min read | 08.21.26
FTC Proposes Enforcement Policy Statement on Personalized Pricing: What Businesses Need to Know
On August 19, 2026, the Federal Trade Commission (FTC) announced a proposed Enforcement Policy Statement on personalized pricing — the practice of companies using consumers’ personal data to set individualized prices, discounts, coupons, or other incentives. The proposed statement, which is open for public comment for 30 days following publication in the Federal Register, marks a major step up in the FTC’s focus on data-driven pricing strategies and puts businesses across industries on notice that undisclosed or inadequately disclosed personalized pricing will not be tolerated. Importantly, while the proposed statement is not a binding legal requirement and does not create new legal obligations, it serves as an enforcement warning that the FTC is prepared to use its existing enforcement authority under Section 5 of the FTC Act (Section 5) and is also a potential harbinger of rulemaking. Businesses that engage in — or are considering — personalized pricing should carefully assess their disclosure practices and data collection procedures against the standards articulated in this statement.
Client Alert | 7 min read | 08.19.26
CMS’s Final Rule Bans Federal Medicaid Funding for Youth Gender-Affirming Care
Client Alert | 2 min read | 08.19.26


