1. Home
  2. |Insights
  3. |Not Better Late Than Never: Timing Requirement is Material to Payment

Not Better Late Than Never: Timing Requirement is Material to Payment

Client Alert | 1 min read | 06.15.18

On June 11, 2018, in U.S. ex rel Prather v. Brookdale Senior Living Communities Inc., the Sixth Circuit reversed dismissal of a False Claims Act suit against the country’s largest senior living provider because the relator had sufficiently alleged materiality. The qui tam suit was brought by a former nurse who alleged that physician certifications of patient need for home-health care were not signed until months after the care had been provided, in violation of 42 C.F.R. § 424.22 which requires that such certifications be completed at the time a plan of care is established or “as soon thereafter as possible.”

Applying the factors that the Supreme Court identified in its Escobar decision, the Sixth Circuit held in a 2-1 decision that the relator sufficiently pleaded that the timing requirement in § 424.22 was material by alleging that it was an express condition of payment and referring to guidance documents suggesting that compliance with the timing requirement went to the “essence of the bargain” between the defendants and the government. Notably, the lower court had drawn a negative inference on materiality because the complaint contained no allegations about the government’s past practice vis-à-vis claims that did not comply with the timing requirement in § 424.22. The Sixth Circuit found that this was “one step too far” because although past government actions are relevant to the materiality analysis, they are not dispositive.

Insights

Client Alert | 1 min read | 08.10.26

ASBCA Denies Government Motion to Dismiss, Providing Key Guidance on Contractor Claim Standards Post-ECC International

In Appeal of Bahadir (a C&M case), the Armed Services Board of Contract Appeals denied the government’s motion to dismiss in its entirety, ruling in favor of the contractor on both key issues raised by the government. The case arises from a contract for construction work at Al Udeid Air Base in Qatar, under which Appellant alleged government-caused delay and filed certified prolongation claims using a “windows analysis” methodology. The government moved to dismiss, arguing that Appellant failed to state a sum certain for each of what the government characterized as 38 distinct claims, and separately that four claims had not been properly presented to the Contracting Officer. ...