Federal Circuit Affirms Board Decision on Pandemic-Related Claim
Client Alert | 2 min read | 06.21.21
The Federal Circuit recently affirmed the Civilian Board of Contract Appeals’ (CBCA) decision denying a pandemic-related claim in Pernix Serka Joint Venture v. Secretary of State, CBCA No. 5683, 20-1 BCA ¶ 37,589. Pernix involved a firm-fixed-price construction contract in Sierra Leone that was impacted by an Ebola outbreak several months into the project. The Department of State (DOS) declined to provide direction or to issue a suspension of work order, and instead advised Pernix to make its own business decisions regarding performance and employee safety. Pernix chose to demobilize its workforce and, later, to remobilize with the addition of its own on-site medical facility and services. Pernix then submitted a claim for the increased medical, safety, and demobilization and remobilization costs. DOS granted an adjustment to the schedule for the Ebola-related delays under the contract’s excusable delay clause, but denied Pernix’s monetary claim.
At the CBCA, Pernix argued that the Ebola outbreak resulted in a cardinal change, a constructive change, and/or a constructive suspension of work. The Board rejected each argument. First, the Board held that a cardinal change cannot occur when the work required by the contract is unchanged (and the Board found that the additional medical and safety precautions did not change the fundamental construction work required under the contract). Second, the Board held there was no constructive change in the absence of direction from the Government, and noted that the Government permitted Pernix additional time to perform. Third, the Board dismissed Pernix’s constructive suspension of work argument because it had not been presented to the contracting officer in Pernix’s certified claim.
Pernix appealed to the Federal Circuit. However, on June 9, 2021, the Circuit affirmed the Board’s decision in a one-line summary Rule 36 decision. Although the Federal Circuit did not address the specific issues and legal theories in Pernix’s claim, the summary decision is a reminder to contractors that actions taken in the absence of government direction may potentially be treated as business decisions, even if they were intended to safeguard employee health during a pandemic. Moreover, contractors should be aware that even where they may be entitled to time extensions, they may not necessarily be entitled to additional costs. Thus, as always, contractors who anticipate submitting claims should carefully consider and consult with counsel regarding potential legal theories for recovery and, where possible, ground those theories in specific direction from the cognizant Government contracting officer.
Contacts
Insights
Client Alert | 3 min read | 06.03.26
Important EU Court Judgment Clarifies Rules on Interest Due in Cartel Damages Cases
In a judgment that will have direct and immediate consequences, the Court of Justice of the European Union (CJEU) has clarified that for all competition damages actions brought after 26 December 2014, interest runs from the date on which the harm occurred. The ruling addressed two important questions: (1) whether national provisions implementing Article 3(2) of the EU Damages Directive — which requires interest to run from the date harm occurred —apply to cases in which the harm preceded the adoption of those provisions; and (2) how the date of harm should be determined in cartel cases involving the purchase of goods at inflated prices.
Client Alert | 2 min read | 06.02.26
SBA OHA Confirms That the Submission Date for a Proposal with Pricing Controls Size Determination
Client Alert | 5 min read | 06.01.26
California Court Upholds Insurer’s Duty to Defend After Covered Claim Is Dismissed
Client Alert | 2 min read | 05.29.26
California Assembly Passes AB 1776, Sending Major Antitrust Bill to the Senate





