Federal Circuit Affirms Board Decision on Pandemic-Related Claim
Client Alert | 2 min read | 06.21.21
The Federal Circuit recently affirmed the Civilian Board of Contract Appeals’ (CBCA) decision denying a pandemic-related claim in Pernix Serka Joint Venture v. Secretary of State, CBCA No. 5683, 20-1 BCA ¶ 37,589. Pernix involved a firm-fixed-price construction contract in Sierra Leone that was impacted by an Ebola outbreak several months into the project. The Department of State (DOS) declined to provide direction or to issue a suspension of work order, and instead advised Pernix to make its own business decisions regarding performance and employee safety. Pernix chose to demobilize its workforce and, later, to remobilize with the addition of its own on-site medical facility and services. Pernix then submitted a claim for the increased medical, safety, and demobilization and remobilization costs. DOS granted an adjustment to the schedule for the Ebola-related delays under the contract’s excusable delay clause, but denied Pernix’s monetary claim.
At the CBCA, Pernix argued that the Ebola outbreak resulted in a cardinal change, a constructive change, and/or a constructive suspension of work. The Board rejected each argument. First, the Board held that a cardinal change cannot occur when the work required by the contract is unchanged (and the Board found that the additional medical and safety precautions did not change the fundamental construction work required under the contract). Second, the Board held there was no constructive change in the absence of direction from the Government, and noted that the Government permitted Pernix additional time to perform. Third, the Board dismissed Pernix’s constructive suspension of work argument because it had not been presented to the contracting officer in Pernix’s certified claim.
Pernix appealed to the Federal Circuit. However, on June 9, 2021, the Circuit affirmed the Board’s decision in a one-line summary Rule 36 decision. Although the Federal Circuit did not address the specific issues and legal theories in Pernix’s claim, the summary decision is a reminder to contractors that actions taken in the absence of government direction may potentially be treated as business decisions, even if they were intended to safeguard employee health during a pandemic. Moreover, contractors should be aware that even where they may be entitled to time extensions, they may not necessarily be entitled to additional costs. Thus, as always, contractors who anticipate submitting claims should carefully consider and consult with counsel regarding potential legal theories for recovery and, where possible, ground those theories in specific direction from the cognizant Government contracting officer.
Contacts
Insights
Client Alert | 7 min read | 06.26.26
Federal Roundup: Updates for PBMs and Medicare Advantage Organizations
In June 2026, federal regulators and lawmakers continued their efforts to improve drug affordability through targeted reforms. These recent developments will primarily impact pharmaceutical manufacturers, managed care organizations, and pharmacy benefit managers (PBM) serving Medicare Part D program members. PBMs, Medicare Advantage organizations, and Part D sponsors should monitor these changes in the interest of maintaining compliance and providing input on regulatory proposals that may influence their business operations or compensation structures in the future.
Client Alert | 6 min read | 06.26.26
Client Alert | 4 min read | 06.25.26
Twin Executive Orders Seek to Spur Quantum Leap in Technology and Cybersecurity
Client Alert | 7 min read | 06.24.26





