DOJ's FCPA Pilot Program Issues First Public Declination Under Trump Administration
Client Alert | 2 min read | 06.21.17
Last Friday, the Department of Justice publicly disclosed another declination under its FCPA pilot program. This is the sixth public declination by the Department since first launching the program in April 2016 (as previously discussed in a Crowell & Moring alert). It also represents the first public declination since the Department announced the temporary extension of the pilot program on March 10, 2017, and the first under the new administration.
The Facts
In its June 16th letter to counsel for Linde North America Inc. and Linde Gas North America LLC, the Department outlined a series of factual findings related to Linde’s FCPA violations. It attributes the offending conduct to Spectra Gases, Inc., a New Jersey company acquired by Linde in October 2006, and states that between approximately November 2006 through December 2009, Linde—through Spectra—"made corrupt payments to high-level officials at the National High Technology Center (NHTC) of the Republic of Georgia, a 100 percent state-owned and -controlled entity, in connection with its purchase of certain income-producing assets from the NHTC." The alleged scheme involved three high-level Spectra executives agreeing to a profit-sharing arrangement with high-level NHTC officials. Namely, in exchange for the officials’ assistance in ensuring that Spectra was selected as the purchaser of key NHTC assets, the Spectra executives agreed to share profits resulting from future sales with those officials. Ultimately, the NHTC officials "received approximately 75 percent of the profits generated by" Spectra’s arrangement with NHTC. Prior to discovering the misconduct, Linde dissolved Spectra, became its successor-in-interest, and continued to benefit "as a result of the corrupt conduct."
Cooperation, Cooperation, Cooperation:
Consistent with prior declinations, the Department credited a number of examples of Linde’s cooperation that factored into the declination, including: "Linde’s voluntary self-disclosure of the matter;" "the thorough, comprehensive and proactive investigation undertaken by Linde;" "Linde’s full cooperation in the matter (including its provision of all known relevant facts about the individuals involved in or responsible for the misconduct) and its agreement to continue to cooperate in any ongoing investigations of individuals;" "the steps Linde has taken and continues to take to enhance its compliance program and its internal accounting controls" and "Linde’s full remediation" described as "including terminating and/or taking disciplinary action against the employees involved in the misconduct, including the Spectra Executives and lower-level employees involved in the misconduct)," withholding certain payments from the executives, and terminating a management agreement with and withholding payments from "companies owned or controlled by the NHTC Officials."
About the Money
Although Linde successfully avoided criminal prosecution, it also agreed to disgorge $7.8 million (representing profits and benefits received by Spectra and, subsequently, Linde) and to forfeit an additional $3.4 million (representing "corrupt proceeds owed to companies owned or controlled by the NHTC Officials"). Linde’s agreement to continue cooperating means that the financial costs may yet increase, and the Department is at least telegraphing that it intends to continue investigating the individuals involved.
Cautionary Tale
Linde got to the right result in this matter, but the cost of getting there was not cheap. Like other matters, this FCPA declination is a stark reminder of the importance of pre-acquisition due diligence.
Contacts
Insights
Client Alert | 3 min read | 10.15.25
On August 15, 2025, the Treasury Department and IRS released updated guidance concerning Beginning of Construction requirements to qualify for clean energy tax credits. This new guidance is critical for developers to consider as they rush to qualify for the tax credits before they expire entirely. The much-anticipated guidance followed the July 7, 2025 Executive Order 14315, Ending Market Distorting Subsidies for Unreliable, Foreign-Controlled Energy Sources (“July 7, 2025 Executive Order”), which signaled that the Trump Administration was planning to strictly enforce the termination of production and investment tax credits for solar and wind facilities that are set to expire under the One Big Beautiful Bill Act (OBBB Act), covered in more detail here. The new guidance comes at a time when many in the industry are struggling to keep up with the myriad ways that the new administration is working to roll back wind and solar tax credits, leaving developers to piece through the recent guidance to determine how best to structure and invest in clean energy projects given the volatile position of the current administration vis-a-vis wind and solar energy.
Client Alert | 10 min read | 10.15.25
Client Alert | 4 min read | 10.14.25
Client Alert | 35 min read | 10.13.25
Building Blocks of Design Law: CJEU rules on LEGO Group Modular Design Protection