1. Home
  2. |Insights
  3. |A Rose and a Thorn: Federal Circuit Permits Contractor to Add New Claim to Pending Complaint, but Enforces Notice Provision to Bar Recovery

A Rose and a Thorn: Federal Circuit Permits Contractor to Add New Claim to Pending Complaint, but Enforces Notice Provision to Bar Recovery

Client Alert | 1 min read | 02.26.15

In K-Con Building Systems Inc. v. United States, the Federal Circuit held that a contractor could amend its COFC complaint to add new, denied claims related to the appeal if the new claims either requested different remedies (e.g., additional compensation, remission of funds, non-monetary relief) or asserted legal grounds for relief that were materially different from the claims under appeal. This holding may prove helpful to contractors at the COFC who identify additional bases for recovery/remedies after filing their complaint; however, the Court also denied recovery because the contractor's two-year delay before notifying the government of the alleged "changes" failed to provide the adequate notice required by the Changes Clause, distinguishing the facts in K-Con from those in prior cases where notice provisions were not strictly enforced.

Insights

Client Alert | 3 min read | 06.03.26

Important EU Court Judgment Clarifies Rules on Interest Due in Cartel Damages Cases

In a judgment that will have direct and immediate consequences, the Court of Justice of the European Union (CJEU) has clarified that for all competition damages actions brought after 26 December 2014, interest runs from the date on which the harm occurred. The ruling addressed two important questions: (1) whether national provisions implementing Article 3(2) of the EU Damages Directive — which requires interest to run from the date harm occurred —apply to cases in which the harm preceded the adoption of those provisions; and (2) how the date of harm should be determined in cartel cases involving the purchase of goods at inflated prices....