1. Home
  2. |Insights
  3. |Too Late: Government’s Failure to Timely Audit Did Not Extend the Contractor’s Document Retention Obligations

Too Late: Government’s Failure to Timely Audit Did Not Extend the Contractor’s Document Retention Obligations

Client Alert | 2 min read | 10.03.22

In Doubleshot, Inc., ASBCA No. 61691 (July 19, 2022), the Armed Services Board of Contract Appeals (“ASBCA”) granted the contractor’s motion for partial summary judgment, denying the Government’s claim for unallowable costs to the extent that it was based on missing or unsigned employee time cards.  The ASBCA held that the contractor was not required to maintain time card records to support the allowability of labor charges beyond the retention period specified in the contractor’s cost-plus-fixed-fee contracts (including applicable time extensions). 

The contracts incorporated both the Audit and Records – Negotiation clause (FAR 52.215-2) and the Allowable Cost and Payment clause (FAR 52.216-7), which grant the Government the right to examine the contractor’s records reflecting all claimed costs and reduce payments for amounts that are unallowable.  Following the contractor’s delayed submission of two final indirect cost rate proposals, the Defense Contract Audit Agency (“DCAA”) did not begin auditing the proposals until eight months after the contractual obligation to maintain records had expired.  DCAA then questioned the contractor’s labor costs for which there was no time card support, even though the contractor was able to demonstrate that it paid its employees.  The Government’s claim and the contractor’s appeal followed. 

The ASBCA held that the contractor was not obligated to keep time card records beyond the FAR-mandated retention periods set in the contracts.  Therefore, the Government could not disallow the costs on the basis that the time cards were unavailable.  In so holding, the ASBCA rejected the Government’s argument that applying the FAR criteria was unfair, noting that the records retention period is a product of Government regulations and part of a FAR clause incorporated by the contracting officer.  The ASBCA also denied the portion of the Government’s claim that relied on unsigned time cards, noting that the FAR’s documentation requirement does not require signed time cards in order to support cost allowability.   

In sum, the ASBCA will not de facto extend document retention requirements by permitting a Government claim for unallowable costs on the basis of insufficient supporting documentation.  By contrast, the CBCA recently indicated, in dicta in Mission Support Alliance, CBCA 6477, that if presented with similar facts and arguments, it may hold differently.    

Insights

Client Alert | 4 min read | 12.04.25

District Court Grants Preliminary Injunction Against Seller of Gray Market Snack Food Products

On November 12, 2025, Judge King in the U.S. District Court for the Western District of Washington granted in part Haldiram India Ltd.’s (“Plaintiff” or “Haldiram”) motion for a preliminary injunction against Punjab Trading, Inc. (“Defendant” or “Punjab Trading”), a seller alleged to be importing and distributing gray market snack food products not authorized for sale in the United States. The court found that Haldiram was likely to succeed on the merits of its trademark infringement claim because the products at issue, which were intended for sale in India, were materially different from the versions intended for sale in the U.S., and for this reason were not genuine products when sold in the U.S. Although the court narrowed certain overbroad provisions in the requested order, it ultimately enjoined Punjab Trading from importing, selling, or assisting others in selling the non-genuine Haldiram products in the U.S. market....