"Yardstick" Measures Failure to Progress in A-12 Default Termination
Client Alert | 1 min read | 05.11.07
In the latest opinion in the 16-year A-12 litigation, McDonnell Douglas Corp. v. United States, No. 91-1204C (Fed. Cl. May 3, 2007) the Court of Federal Claims, on remand from the Federal Circuit, upheld default termination of the fixed-price research and development contract based upon a failure to make progress -- even though the full contract "had no completion date at [the time of] termination." With no completion date for the full contract, the Court instead used a "yardstick" to measure the contractors' progress, holding that (1) the Court could use a series of interim deadlines for the production of prototype aircraft to define both the "performance required" and the "time remaining for performance"; and (2) at the time of termination, there was sufficient information available for the contracting officer to have concluded there was no reasonable likelihood of delivery under those deadlines (even if the contracting officer did not, in the event, make the default termination decision based upon that "available" information).
Contacts
Insights
Client Alert | 2 min read | 07.24.26
GAO Finds That Challenge to Agency’s Failure to Comply With DFARS Requirement Comes Too Late
GAO’s recent dismissal of the protest in Tyonek Technical Innovations, LLC, B-424364, B-424364.2, June 30, 2026, carries an important lesson for government contractors: if you believe solicitation terms conflict with a statute or regulation, you must raise that challenge before proposals are due—not during discussions or afterwards.
Client Alert | 3 min read | 07.23.26
Client Alert | 3 min read | 07.23.26
Second Circuit Affirms Preliminary Injunction Against Nielsen in Constructive Tying Case
Client Alert | 4 min read | 07.22.26