  3. |Too Late: Another Government Claim Barred by CDA Statute of Limitations

Too Late: Another Government Claim Barred by CDA Statute of Limitations

Client Alert | 1 min read | 06.09.14

In Laguna Constr. (May 29, 2014), the ASBCA barred the government's claim under the CDA statute of limitations when DCAA had issued a report, more than six years prior, finding that the contractor's subcontract management system was "inadequate" and resulted in "a significant risk . . . relative to allocability, allowability, and reasonableness of subcontract costs billed to the U.S. Government." Even though that report did not identify any specific government claim, the Board found that the government knew or should have known of the basis for its specific claim "no later than" the date that DCAA provided the report to the ACO with its general criticisms, emphasizing that the "events fixing liability should have been known when they occurred unless they can be reasonably found to have been either concealed or 'inherently unknowable' at that time," the latest in a string of decisions interpreting the CDA statute of limitations as to government cost claims (discussed here, here, here, here, here, and here).


Insights

Client Alert | 3 min read | 06.03.26

Important EU Court Judgment Clarifies Rules on Interest Due in Cartel Damages Cases

In a judgment that will have direct and immediate consequences, the Court of Justice of the European Union (CJEU) has clarified that for all competition damages actions brought after 26 December 2014, interest runs from the date on which the harm occurred. The ruling addressed two important questions: (1) whether national provisions implementing Article 3(2) of the EU Damages Directive — which requires interest to run from the date harm occurred —apply to cases in which the harm preceded the adoption of those provisions; and (2) how the date of harm should be determined in cartel cases involving the purchase of goods at inflated prices....