1. Home
  2. |Insights
  3. |Subcontractor Must Intend That Government Pay False Claim Submitted To Prime, Supreme Court Rules

Subcontractor Must Intend That Government Pay False Claim Submitted To Prime, Supreme Court Rules

Client Alert | 1 min read | 06.10.08

The Supreme Court's unanimous decision this week in Allison Engine Co. v. United States ex rel. Sanders (June 9, 2008, http://www.supremecourtus.gov/opinions/07pdf/07-214.pdf), interprets section 3729(a)(2) of the federal civil False Claims Act (imposing treble damages and penalties on anyone who "knowingly makes [or] uses … a false record or statement to get a false or fraudulent claim paid by the Government") in a way likely to increase the difficulty of pursuing FCA allegations against government subcontractors such as those in this case, who allegedly submitted false certificates of conformance to the primes and higher-tier subs under Navy shipbuilding contracts. The Court stated, (1) that 3729(a)(2) includes an intent requirement, i.e., the plaintiff must prove that the subcontractor defendant intended that the government pay a false claim in reliance on the sub's false statements to the prime, and (2) that although section (a)(2), unlike section (a)(1), does not require proof that the defendant "presented" a false claim to the government, (3) it still is not sufficient under (a)(2) simply to prove that a sub's false statement "resulted in the use of Government funds to pay a false or fraudulent claim," because if that were so, "almost boundless" FCA liability could attach to any fraud against a private party as long as the victim had received some federal funds.

Insights

Client Alert | 1 min read | 08.10.26

ASBCA Denies Government Motion to Dismiss, Providing Key Guidance on Contractor Claim Standards Post-ECC International

In Appeal of Bahadir (a C&M case), the Armed Services Board of Contract Appeals denied the government’s motion to dismiss in its entirety, ruling in favor of the contractor on both key issues raised by the government. The case arises from a contract for construction work at Al Udeid Air Base in Qatar, under which Appellant alleged government-caused delay and filed certified prolongation claims using a “windows analysis” methodology. The government moved to dismiss, arguing that Appellant failed to state a sum certain for each of what the government characterized as 38 distinct claims, and separately that four claims had not been properly presented to the Contracting Officer. ...