No Prime Liability = No Pass-Through
Client Alert | less than 1 min read | 05.06.08
The Court of Federal Claims in Harper/Nielsen Dillingham, Builders v. U.S. (Apr. 29, 2008) denied a contractor's suit against the government in which it sought to pass through subcontractor claims for cost increases caused by government delays. The court acknowledged that the "Severin doctrine" allows such pass-through claims when the prime contractor is potentially liable to its subcontractor for the damages, but here found the prime could not be liable because the subcontract included an "iron-bound bar" against such liability due to a "no damage for delay" clause.
Contacts
Insights
Client Alert | 3 min read | 02.26.26
FERC Requires Refunds for Late QF Recertification
On February 19, 2026, the Federal Energy Regulatory Commission (FERC) issued Branch Street Solar Partners, LLC et al., 194 FERC ¶ 61,124 (2026) rejecting the refund reports filed in connection with the late filing of recertifications of qualifying facility (QF) status by certain affiliated companies to reflect a change in upstream ownership. FERC’s rearticulation of QF recertification timing requirements and consequences for late QF recertifications has broad and substantial implications for all QF owners.
Client Alert | 4 min read | 02.26.26
Client Alert | 6 min read | 02.24.26
Artificial Intelligence and Human Resources in the EU: a 2026 Legal Overview
Client Alert | 3 min read | 02.24.26
DOJ v. OhioHealth Confirms Antitrust Enforcers’ Continued Focus on Health Care Markets

