Limitations Of Cost Notice Obligations Must Be Met
Client Alert | less than 1 min read | 09.15.06
The ASBCA in International Technology Corp. (July 17, 2006), denied a claim for an upward adjustment above the contract's cost limitation because the contractor had inexcusably failed to comply with the Limitation of Cost clause provision requiring advance notice to the government of the projected costs over the limit. The board rejected the contractor's argument that it had to determine the allowability of its subcontractor's costs prior to providing notice, finding that notice is required when a contractor has “reason to believe” there will be a cost increase.
Insights
Client Alert | 7 min read | 06.24.26
On June 17, 2026, the U.S. Department of Justice’s (DOJ( National Security Division (NSD) announced that it had issued a declination for Robert Bosch GmbH (Bosch) relating to potential violations of the Export Control Reform Act, 50 U.S.C. § 4819 (ECRA). Specifically, the DOJ declined to criminally prosecute Bosch’s violations of the Export Administration Regulations’ (EAR) Foreign Direct Product Rule (FDPR), which apparently resulted from two Bosch subsidiaries’ export of products and software manufactured with equipment that was the direct product of U.S. software or technology to Huawei Technologies Co., Ltd. and its “Entity List” affiliates, including Huawei Tech. Investment Co., Ltd., Hong Kong (collectively, Huawei). The same day, the U.S. Department of Commerce Bureau of Industry and Security (BIS) announced a parallel civil administrative settlement with Bosch.
Client Alert | 3 min read | 06.24.26
Client Alert | 4 min read | 06.23.26
EPA Hands Over AI Data Center Regulation to States and Communities to Develop Best Practices
Client Alert | 3 min read | 06.22.26
