1. Home
  2. |Insights
  3. |Limitations Of Cost Notice Obligations Must Be Met

Limitations Of Cost Notice Obligations Must Be Met

Client Alert | less than 1 min read | 09.15.06

The ASBCA in International Technology Corp. (July 17, 2006), denied a claim for an upward adjustment above the contract's cost limitation because the contractor had inexcusably failed to comply with the Limitation of Cost clause provision requiring advance notice to the government of the projected costs over the limit. The board rejected the contractor's argument that it had to determine the allowability of its subcontractor's costs prior to providing notice, finding that notice is required when a contractor has “reason to believe” there will be a cost increase.

Insights

Client Alert | 3 min read | 11.13.26

Massachusetts Trade Secret Preliminary Injunctions: Prove the Harm, Tailor the Relief

A strong trade secret claim is not a substitute for proof of irreparable harm. In Daikin Applied Americas Inc. v. Russo, No. SJC-13881 (Mass. Oct. 14, 2026), the Massachusetts Supreme Judicial Court held that likely success on a misappropriation claim does not create a presumption of irreparable harm. The court grounded its ruling in both the Massachusetts Uniform Trade Secrets Act and the traditional equitable principles the statute incorporates. It required a case-specific showing that the requested relief would prevent harm that a final judgment could not adequately remedy. ...