1. Home
  2. |Insights
  3. |Limitation on Mark-Up of Subcontractor Costs

Limitation on Mark-Up of Subcontractor Costs

Client Alert | less than 1 min read | 04.30.07

In an interim rule effective immediately, the Defense Department amended DFARS on April 26, 2007 to permit the Government to "disallow" (including on firm-fixed price contracts) "excessive pass through charges" on subcontracts where the total subcontract costs exceeds 70 percent of the contract value. "Excessive" charges are defined to include costs and profit that the contractor cannot demonstrate to the contracting officer add something other than "no or negligible" substantive value to performance, so any contractor with an accounting practice that allocates G&A to subcontract costs could run afoul of these rules.

Insights

Client Alert | 19 min read | 12.18.25

2025 GAO Bid Protest Annual Report: Where Have All the Protests Gone?

On December 12, 2025, the U.S. Government Accountability Office (GAO) released its annual report on bid protests for fiscal year 2025, containing the full statistics shown below:...