GAO Finds Discussions Were Not Meaningful And, In Fact, Misleading
Client Alert | 1 min read | 06.30.04
In Lockheed Martin Corp. (May 27, 2004), GAO found that the agency failed to conduct meaningful discussions because it neglected to notify the protester during discussions that proposed "contractor-specific" savings would be excluded from the agency's calculation of the Average Unit Production Cost ("AUPC"), despite the protester's reasonable belief that the agency would do so, and further, that discussions were misleading because the agency failed to disabuse the protester of its erroneous (though reasonable) understanding regarding the costs that the agency intended to apply in calculating the AUPC. GAO also determined that the award decision was flawed because the agency credited the awardee's proposal with having met certain performance requirements even though the proposal never addressed the specific level of performance required.
Contacts
Insights
Client Alert | 2 min read | 07.24.26
GAO Finds That Challenge to Agency’s Failure to Comply With DFARS Requirement Comes Too Late
GAO’s recent dismissal of the protest in Tyonek Technical Innovations, LLC, B-424364, B-424364.2, June 30, 2026, carries an important lesson for government contractors: if you believe solicitation terms conflict with a statute or regulation, you must raise that challenge before proposals are due—not during discussions or afterwards.
Client Alert | 3 min read | 07.23.26
Client Alert | 3 min read | 07.23.26
Second Circuit Affirms Preliminary Injunction Against Nielsen in Constructive Tying Case
Client Alert | 4 min read | 07.22.26

