GAO Dismisses Subcontract Protest
Client Alert | less than 1 min read | 05.19.04
Noting that its protest jurisdiction extends only to awards “by a Federal agency,” in Addison Construction, Inc., B-293805, April 20, 2004, GAO dismissed the protest because the prime contractor evaluated the proposals and made the award decision. However, GAO noted it would take jurisdiction if the agency handled all the substantive aspects of the procurement, even if the prime contractor handled the procedural aspects, such as issuing the solicitation and receiving proposals.
Insights
Client Alert | 3 min read | 03.02.26
Clinical trial sponsors and all other stakeholders involved in conducting commercial clinical trials of investigational medicinal products (IMP) in the UK.
Client Alert | 4 min read | 03.02.26
Client Alert | 3 min read | 02.27.26
Client Alert | 6 min read | 02.27.26
