Contractor Must Actually Receive Final Decision To Start The Clock
Client Alert | less than 1 min read | 05.20.05
The Federal Circuit in Riley & Ephriam Constr. Co. (May 18, 2005) emphasized that the Contract Disputes Act requires actual delivery of the final decision to the contractor or its designated agent before the time to file an appeal at the board or a case in the Court of Federal Claims starts to run. In this case, the Federal Circuit rejected as "receipt" by the contractor both delivery to a P.O. box and a fax transmission sheet to the contractor's attorney when receipt of the fax was denied and the CO did not follow up to confirm receipt personally.
Insights
Client Alert | 3 min read | 11.13.26
Massachusetts Trade Secret Preliminary Injunctions: Prove the Harm, Tailor the Relief
A strong trade secret claim is not a substitute for proof of irreparable harm. In Daikin Applied Americas Inc. v. Russo, No. SJC-13881 (Mass. Oct. 14, 2026), the Massachusetts Supreme Judicial Court held that likely success on a misappropriation claim does not create a presumption of irreparable harm. The court grounded its ruling in both the Massachusetts Uniform Trade Secrets Act and the traditional equitable principles the statute incorporates. It required a case-specific showing that the requested relief would prevent harm that a final judgment could not adequately remedy.
Client Alert | 1 min read | 11.12.26
SBA Announces Doubling Veteran Contracting Target to 10% for FY 2027, but Questions Remain
Client Alert | 6 min read | 11.12.26
Client Alert | 2 min read | 11.11.26
President Trump Nominates Peter Feldman to Serve as CPSC Chairman and Commissioner
