1. Home
  2. |Insights
  3. |Contractor Must Actually Receive Final Decision To Start The Clock

Contractor Must Actually Receive Final Decision To Start The Clock

Client Alert | less than 1 min read | 05.20.05

The Federal Circuit in Riley & Ephriam Constr. Co. (May 18, 2005) emphasized that the Contract Disputes Act requires actual delivery of the final decision to the contractor or its designated agent before the time to file an appeal at the board or a case in the Court of Federal Claims starts to run. In this case, the Federal Circuit rejected as "receipt" by the contractor both delivery to a P.O. box and a fax transmission sheet to the contractor's attorney when receipt of the fax was denied and the CO did not follow up to confirm receipt personally.

Insights

Client Alert | 8 min read | 12.10.25

Creativity You Can Use: CJEU Clarifies Copyright for Applied Art

On 4 December 2025, the Court of Justice of the EU (CJEU) issued a landmark judgment in the joined cases C-580/23 (Mio v. Asplund) and C-795/23 (USM v. Konektra) concerning copyright protection for “works of applied art” (i.e., utilitarian objects such as tables, furniture, lighting fixtures, sofas, chairs, kitchen appliances, vases, and fashion items)....