1. Home
  2. |Insights
  3. |Contractor Must Actually Receive Final Decision To Start The Clock

Contractor Must Actually Receive Final Decision To Start The Clock

Client Alert | less than 1 min read | 05.20.05

The Federal Circuit in Riley & Ephriam Constr. Co. (May 18, 2005) emphasized that the Contract Disputes Act requires actual delivery of the final decision to the contractor or its designated agent before the time to file an appeal at the board or a case in the Court of Federal Claims starts to run. In this case, the Federal Circuit rejected as "receipt" by the contractor both delivery to a P.O. box and a fax transmission sheet to the contractor's attorney when receipt of the fax was denied and the CO did not follow up to confirm receipt personally.

Insights

Client Alert | 4 min read | 06.23.26

EPA Hands Over AI Data Center Regulation to States and Communities to Develop Best Practices

The nation’s power grid and infrastructure are facing increased pressure from artificial intelligence (AI) data centers, prompting new questions around environmental regulatory design and compliance. As technology companies race to build and expand new data center factories, they face a web of permitting requirements as well as potential community opposition, and environmental litigation — all against a backdrop of rapid and still-evolving agency guidance....