Bad Estimates Support Constructive Change Without Proof of Government Negligence
Client Alert | 1 min read | 07.10.13
In IAP World Servs., Inc. v. Dep't of Treasury (June 20, 2013), the Civilian Board of Contract Appeals held the government liable when a maintenance contractor's service calls took longer to perform than calls in historical data furnished to prospective offerors and the government had said the historical data were a "reasonable basis" for firm-fixed-price proposals. Finding that the contractor had relied on the faulty data to price its proposal and that the contractor need not prove government negligence, the CBCA decided that the longer service calls were a constructive change to the contract and awarded the contractor its increased costs of performance.
Insights
Client Alert | 4 min read | 08.21.25
FLSA Overtime Reporting and Withholding
The One Big Beautiful Bill Act (the Act), signed on July 4, 2025, allows a deduction from an individual’s personal tax return on Form 1040 for “qualified overtime compensation” as defined in new Code § 225. The amount that can be deducted from the employee’s return is capped at $12,500 with the maximum then adjusted down if the employee’s AGI exceeds certain limits. This deduction is permitted in 2025.
Client Alert | 4 min read | 08.20.25
Client Alert | 15 min read | 08.20.25
Client Alert | 2 min read | 08.19.25