In Appeal of Colonna's Shipyard, Inc. (June 24, 2010), the ASBCA confirmed, consistent with recent CFC decisions in Todd Construction, L.P. v. U.S., 88 Fed. Cl. 34, 235 (2008), that it has jurisdiction to review claims challenging inaccurate past performance evaluations under the Contract Disputes Act. Thus, the way is clear for contractors to challenge DOD past performance evaluations in either forum.

Contacts

Insights

Client Alert | 3 min read | 06.22.26

Timing Is Everything: GAO Dismisses Three Protests Filed Before the Solicitation Deadline but After GAO’s Daily Cutoff Time

A recent U.S. Government Accountability Office (GAO) decision dismissing three pre-award protests as untimely highlights an important procedural trap for would-be protesters. In Oready, LLC, GAO dismissed three protests filed one business day too late, even though they were submitted prior to the solicitation closing date and time. ...