A Sewer By Any Other Name Would Smell As Foul

Client Alert | 1 min read | 03.24.05

Southwest Marine, Inc. (Feb. 23, 2005), concerned costs incurred by a contractor in defending a private action brought under the Clean Water Act in which the government did not intervene and in which a federal court found that the contractor had violated the act, imposed a penalty for that violation, and then remitted the penalty entirely in recognition of costs incurred by the contractor to correct the violation. The ASBCA acknowledged that there was no FAR provision that expressly made the costs of a private action unallowable, but noted that FAR 31.205-47 would make such costs unallowable if the action had been brought by the government and concluded that the costs incurred in this private action were sufficiently similar to costs incurred in an action brought by the government to make the costs of the private action unallowable as well.

Insights

Client Alert | 2 min read | 07.15.26

CMMC Phase II Suspension Requires Reconsideration of Such Requirements in Solicitations

As discussed in more detail here, the U.S. Department of War (DoW) recently issued a memorandum (Memo 26-P-1023, dated July 13, 2026) directing the immediate suspension of Cybersecurity Maturity Model Certification (CMMC) Phase II requirements (Level I and II self assessments are still permitted). Significantly, the memo directs that “all pending and future CMMC implementation milestones across DoW solicitations and contracts are held in abeyance until further notice.” Moreover, the DoW issued a memorandum on implementing these requirements (available here), directing agencies to issue amendments removing CMMC Level 2 and 3 requirements from active solicitations “as soon as practicable.” Contractors should monitor the government’s compliance with this requirement and should be prepared, if needed, to file a bid protest to protect their rights....