1. Home
  2. |Insights
  3. |Show Me The Money (Or GFE): FAR 52.245-1 Required Contracting Officer to Consider Equitable Adjustment for Missing Equipment

Show Me The Money (Or GFE): FAR 52.245-1 Required Contracting Officer to Consider Equitable Adjustment for Missing Equipment

Client Alert | 2 min read | 01.12.21

In BGT Holdings, Inv. v. United States, No. 1:18-cv-00178-PEC (Fed. Cir. Dec. 23, 2020), the Federal Circuit held that FAR 52.245-1 requires the Government to consider an equitable adjustment when it fails to provide Government-furnished equipment (GFE) required by the contract.  The contract in question required the Government to furnish equipment for the construction and delivery of a gas turbine generator.  After award, the Government stated that it would not provide the contractually-required equipment, unless BGT reduced the contract price.  In response, the contractor purchased the equipment itself, and sought reimbursement under FAR 52.245-1.  FAR 52.245-1 grants the Government the right to change the amount of GFE it provides, but also states that the CO “shall consider” an equitable adjustment under the contract.  The Government did not grant an equitable adjustment, and BGT asserted several theories related to FAR 52.245-1.  The Court of Federal Claims agreed with the Government that BGT’s breach count was insufficiently pled because, under FAR 52.245-1, the contracting officer must only “consider” the equitable adjustment––with any adjustment allowance being discretionary––and thus a decision to deny an adjustment is not a breach. 

The Federal Circuit reversed.  First, the Court held that the Government’s interpretation of “shall consider” an equitable adjustment would “produce absurd results” and provide the Government with the “unfettered right to withdraw promised GFE from a contract without consequence.”  The Court remanded for a determination of whether the contractor was “entitled to an equitable adjustment as fair compensation for the [Government’s] failure to deliver those GFE items.”  Second, the Court remanded to the trial court to determine whether the contracting office “ratified” the actions of subordinates who communicated with the contractor about the GFE.  The Court held that the contractor did not “waive” this ratification argument by signing a contract with a Changes clause that admonishes the contractor to only follow the written directions of the contracting officer.  Third, the Court held that the contracting officer can “waive” the Changes clause requirements and thus allow subordinates to give authorized change orders, and the Court remanded on this issue as well.  The Federal Circuit’s decision is an important reminder for contractors that the Government cannot make changes to a contract without ensuring that the contractor is compensated for the impact of those changes.

Insights

Client Alert | 4 min read | 09.10.26

European Commission Publishes Landmark Guidelines on Exclusionary Abuses by Dominant Companies

On 3 September 2026, the European Commission adopted new Guidelines on the application of Article 102 TFEU to abusive exclusionary conduct by dominant undertakings. The Guidelines follow a public consultation on a draft published in August 2024 and reflect substantial stakeholder feedback. They replace the Commission's 2008 Guidance on enforcement priorities (which ceases to apply 30 days after publication of the new guidelines in the Official Journal) and represent the most significant reset of the Commission's Article 102 enforcement framework in nearly two decades. The Commission's stated aim is to set out principles and operational guidance, enhance legal certainty, and help companies self-assess their exclusionary-abuse risk....