No Buyer's Remorse – ASBCA Orders Air Force to Pay for What It Got

Client Alert | 1 min read | 10.09.15

In Honeywell Int'l, Inc. (Sept. 24, 2015), the ASBCA held that the Air Force must pay for two solar arrays that the contractor (represented by C&M) provided under an Energy Savings Performance Contract, even though the Board had earlier determined that certain of the contract's payment terms were "invalid." In finding the Air Force liable under an implied-in-fact contract theory, the Board rejected arguments that the Air Force had never intended to acquire the solar arrays and that the contracting officers had lacked authority to bind the government, explaining that the Air Force, simply by refusing to accept them, could not escape liability for the arrays that were "supplied … as designed, completed on time, and installed as required."


Insights

Client Alert | 6 min read | 04.29.26

CMS Seeks to Expand Interoperability Requirements to Drug Pre-Authorization (FAQ)

On April 10, 2026, the Centers for Medicare and Medicaid Services (CMS) issued a proposed rule (2026 CMS Interoperability Standards and Prior Authorization for Drugs, or CMS-0062-P) outlining the agency’s plans to impose new interoperability requirements on payors participating in certain Medicare and Medicaid programs. As described by the agency in a recent press release, the proposed rule “builds on” prior rulemaking by clarifying and enhancing interoperability requirements for payors’ prior authorization processes, specifically those associated with coverage requests for pharmaceutical therapies....