Limitations Of Cost Notice Obligations Must Be Met
Client Alert | less than 1 min read | 09.15.06
The ASBCA in International Technology Corp. (July 17, 2006), denied a claim for an upward adjustment above the contract's cost limitation because the contractor had inexcusably failed to comply with the Limitation of Cost clause provision requiring advance notice to the government of the projected costs over the limit. The board rejected the contractor's argument that it had to determine the allowability of its subcontractor's costs prior to providing notice, finding that notice is required when a contractor has “reason to believe” there will be a cost increase.
Insights
Client Alert | 3 min read | 07.13.26
Amici Rally Behind Liberty Global, Urging Tenth Circuit to Rein in Economic Substance Doctrine
Following the 10th Circuit's April 21, 2026, decision affirming the disallowance of Liberty Global’s $2.4 billion deduction under the codified economic substance doctrine, I.R.C. § 7701(o), Liberty Global filed a petition for panel rehearing or rehearing en banc on June 5, 2026. That petition has since drawn significant amicus support from various industry groups representing large taxpayers, as discussed below.
Client Alert | 2 min read | 07.13.26
Department of War Immediately Suspends CMMC Phase II Requirements, Launches 60-Day Reform Review
Client Alert | 3 min read | 07.10.26
Client Alert | 5 min read | 07.10.26
