1. Home
  2. |Insights
  3. |Limitations Of Cost Notice Obligations Must Be Met

Limitations Of Cost Notice Obligations Must Be Met

Client Alert | less than 1 min read | 09.15.06

The ASBCA in International Technology Corp. (July 17, 2006), denied a claim for an upward adjustment above the contract's cost limitation because the contractor had inexcusably failed to comply with the Limitation of Cost clause provision requiring advance notice to the government of the projected costs over the limit. The board rejected the contractor's argument that it had to determine the allowability of its subcontractor's costs prior to providing notice, finding that notice is required when a contractor has “reason to believe” there will be a cost increase.

Insights

Client Alert | 2 min read | 11.14.25

Defining Claim Terms by Implication: Lexicography Lessons from Aortic Innovations LLC v. Edwards Lifesciences Corporation

Claim construction is a key stage of most patent litigations, where the court must decide the meaning of any disputed terms in the patent claims.  Generally, claim terms are given their plain and ordinary meaning except under two circumstances: (1) when the patentee acts as its own lexicographer and sets out a definition for the term; and (2) when the patentee disavows the full scope of the term either in the specification or during prosecution.  Thorner v. Sony Comput. Ent. Am. LLC, 669 F.3d 1362, 1365 (Fed. Cir. 2012).  The Federal Circuit’s recent decision in Aortic Innovations LLC v. Edwards Lifesciences Corp. highlights that patentees can act as their own lexicographers through consistent, interchangeable usage of terms across the specification, effectively defining terms by implication....