LOC Clause Applies To Each Delivery Order, Not Full Contract
Client Alert | 1 min read | 07.30.04
In Analysas Corp. (May 12, 2004), the ASBCA held that, under an indefinite quantity cost-plus-fixed-fee contract for services, the contract’s limitation of cost (“LOC”) clause (which required the contractor to give notice if its costs were expected to exceed 75% of the "estimated cost specified in the Schedule") allowed the government to deny payments to a contractor for costs it incurred in excess of the estimated cost for each delivery order, even though the contractor had not yet exceeded 75% of the maximum total labor hours specified "in the Schedule" for the full contract. The Board reasoned that the contract lacked the “critical provision” of a specific dollar figure "in the Schedule" for the total estimated contract cost, instead allowing for later addition of estimated costs for each delivery order that the government issued.
Contacts
Insights
Client Alert | 2 min read | 07.24.26
GAO Finds That Challenge to Agency’s Failure to Comply With DFARS Requirement Comes Too Late
GAO’s recent dismissal of the protest in Tyonek Technical Innovations, LLC, B-424364, B-424364.2, June 30, 2026, carries an important lesson for government contractors: if you believe solicitation terms conflict with a statute or regulation, you must raise that challenge before proposals are due—not during discussions or afterwards.
Client Alert | 3 min read | 07.23.26
Client Alert | 3 min read | 07.23.26
Second Circuit Affirms Preliminary Injunction Against Nielsen in Constructive Tying Case
Client Alert | 4 min read | 07.22.26

