Inclusion of Deferred Compensation Found Proper Where Government Forced Contractor’s Hand
Client Alert | 1 min read | 08.11.17
In Quimba Software, Inc. v. United States (No. 12-142C), the Court of Federal Claims granted Quimba’s Motion for Summary Judgment, finding that “Quimba’s inclusion of deferred compensations costs in its 2004 [Incurred Cost Proposal] [wa]s allowable under the FAR….” Specifically, while the government argued that the FAR and CAS requirements precluded “deferred compensation for closely held companies ‘except in the year in which the compensation [wa]s paid,’” the Court found that Quimba’s situation fell within the “limited exception” to the IRS deductibility-timing rules because “Quimba’s deferral of its FY 2004 compensation was unintended, unavoidable, and unanticipated[,]” and “Quimba’s financial difficulty, which forced payment of the compensation beyond 2004, was unforeseeable through FY 2004.” In this respect, the Court recognized that the government effectively “forced Quimba’s hand” to defer compensation when it failed to make additional payments beyond the first payment as a result of the government’s “updating and approval process” of Quimba’s accounting system, which took “the entirety of FY 2004 and continue[d] through a significant part of FY 2005.”
Contacts
Insights
Client Alert | 2 min read | 07.24.26
GAO Finds That Challenge to Agency’s Failure to Comply With DFARS Requirement Comes Too Late
GAO’s recent dismissal of the protest in Tyonek Technical Innovations, LLC, B-424364, B-424364.2, June 30, 2026, carries an important lesson for government contractors: if you believe solicitation terms conflict with a statute or regulation, you must raise that challenge before proposals are due—not during discussions or afterwards.
Client Alert | 3 min read | 07.23.26
Client Alert | 3 min read | 07.23.26
Second Circuit Affirms Preliminary Injunction Against Nielsen in Constructive Tying Case
Client Alert | 4 min read | 07.22.26


