Failure to Consider CAS Materiality Criteria Dooms Gov’t Claim
Client Alert | 1 min read | 11.10.16
In Raytheon Co. (ASBCA Aug. 9, 2016), a case involving disallowed cost increases following voluntary accounting changes, the board ruled that the CO violated FAR 30.602 and abused her discretion by considering only the amount of the dollar impact of the accounting changes and, thus, “fail[ed] to analyze the materiality of the cost impacts at issue” pursuant to the criteria set out in CAS 9903.305. Noting (without deciding) that a cost impact of less than 0.005 percent across affected contracts (roughly $142 per contract) might not be “material,” the board held that the government cannot recover on its claim when the CO “simply disregard[s],” rather than evaluates, the CAS materiality factors.
Contacts
Insights
Client Alert | 10 min read | 10.23.25
The EU’s Defense Readiness Roadmap and Omnibus: What are the Implications for Defense Procurement?
On October 16, 2025, the European Commission and the High Representative of the Union for Foreign Affairs and Security Policy presented their Defense Readiness Roadmap 2030 to the EU Member States. This comprehensive plan aims to strengthen European defense capabilities. It follows, and should be read together with, the Commission’s Defense Readiness Omnibus that was published in June 2025. The Omnibus contains a set of proposals to facilitate defense investments and boost EU Member States’ responsiveness to today’s security challenges.
Client Alert | 5 min read | 10.22.25
Sixth Circuit Reaffirms Privilege Protections During Internal Investigations
Client Alert | 4 min read | 10.21.25
Pivot Point for 340B: HRSA Rebate Model Pilot Program Approaches Launch
Client Alert | 5 min read | 10.20.25
What’s new for Belgian Construction Contracts under the New Book 7 of the Civil Code