Don't Assume That A Debriefing Is Continuing After The Initial Session
Client Alert | less than 1 min read | 05.25.05
In New SI, LLC (Nov. 22, 2004, http://www.gao.gov/decisions/bidpro/295209.htm), GAO concluded that a protest was untimely filed when the contractor waited until after it had received agency responses to the contractor's additional questions submitted at the invitation of the Contracting Officer in the course of the initial debriefing session. In response to the contractor's argument that the debriefing was continuing and not concluded until after the agency's response to questions, GAO explained that, “absent affirmative indication from the agency that the debriefing would remain open after the scheduled session, we consider [the debriefing] to have concluded at the end of that [initial] session.”
Contacts
Insights
Client Alert | 3 min read | 02.13.26
In October 2024, the FTC adopted a final rule that substantially modified the HSR form, requiring new categories of information and documents. The final rule was the most significant overhaul of the HSR premerger notification requirements in decades. The new requirements imposed additional time and expense on merging parties, with the FTC estimating that the new form would likely take triple the amount of time to complete than the previous form. Numerous groups, including the U.S. Chamber of Commerce, sued to challenge the rule.
Client Alert | 12 min read | 02.13.26
What Organ Procurement Organizations Need to Know About CMS's New Proposed Rule
Client Alert | 9 min read | 02.12.26
Client Alert | 3 min read | 02.12.26