CBCA Holds that Contractor is Out on a Limb Seeking Claim Preparation Costs, but Grants T4C Partial Victory
Client Alert | 1 min read | 02.11.19
In Woolery Timber Management, Inc. v. Department of Agriculture (CBCA No. 6031), the contractor sought damages for the alleged partial termination of its contract and various other costs, including consulting fees related to the contractor’s preparation of its certified claim and extra time expended as a result of blocked access to a road. With respect to the alleged partial termination, the Board found that it was not, in fact, a termination at all because the parties failed to execute a draft bilateral modification that would have eliminated some work scope, and the contracting officer never unilaterally issued the modification. However, the Board noted that, earlier, the CO had partially terminated for convenience, but that the contractor failed to submit a termination settlement proposal within one year of that earlier termination. That failure was not fatal. The Board explained that because the earlier termination occurred under the commercial items termination for convenience clause (FAR 52.212-4), and not the FAR’s standard termination for convenience clause, there was no one-year time limit and, thus, Woolery still could “pursue a remedy for any increased costs resulting from the…convenience termination.” Regarding Woolery’s cost claims, the Board reiterated that, consistent with Bill Strong, Woolery could not recover its claim preparation costs. Lastly, the Board awarded Woolery half of its idle equipment damages resulting from a service road that was accidentally blocked — despite the fact that the solicitation did not warrant that Woolery could use the road (generally, this language is required to make an excusable delay compensable).
Insights
Client Alert | 3 min read | 07.02.25
USPTO's Upcoming Changes to the Accelerated Examination Program
On June 10, 2025, the United States Patent and Trademark Office (USPTO) published a final rule that will discontinue the Accelerated Examination program for utility applications, beginning July 10, 2025. The final rule also modifies the rules of practice to clarify the grounds for which a petition to make special may be granted and when a fee is required for such a petition. Currently, Applicants have several ways to expedite examination of their patent applications. For example, an Applicant can expedite examination of utility patent applications by either petitioning to make their application special through the Accelerated Examination program or by applying through the Prioritized Patent Examination Program (“Track One” program).
Client Alert | 2 min read | 07.01.25
DoD Establishes New DOGE Approval Process for ITC&MS and A&AS Contracts
Client Alert | 10 min read | 07.01.25
Ninth Circuit Decision Underscores Increasing False Claims Act Risks to U.S. Importers
Client Alert | 8 min read | 06.30.25