Bad Estimates Support Constructive Change Without Proof of Government Negligence
Client Alert | less than 1 min read | 07.10.13
In IAP World Servs., Inc. v. Dep't of Treasury (June 20, 2013), the Civilian Board of Contract Appeals held the government liable when a maintenance contractor's service calls took longer to perform than calls in historical data furnished to prospective offerors and the government had said the historical data were a "reasonable basis" for firm-fixed-price proposals. Finding that the contractor had relied on the faulty data to price its proposal and that the contractor need not prove government negligence, the CBCA decided that the longer service calls were a constructive change to the contract and awarded the contractor its increased costs of performance.
Contacts
Insights
Client Alert | 3 min read | 07.10.26
In Utech, Inc. v. United States, No. 24-1586 (Fed. Cir. June 24, 2026), the U.S. Court of Appeals for the Federal Circuit clarified that in most cases, a pre-award protest must be filed before the proposal submission deadline to avoid the Blue & Gold waiver rule. This decision, while nonprecedential, is in line with U.S. Government Accountability Office (GAO) precedent, which has long held that pre-award protests must be filed before the proposal submission deadline.
Client Alert | 5 min read | 07.10.26
Client Alert | 6 min read | 07.09.26
EU Steel Overcapacity Regulation: New Permanent Measure in Force from 1 July 2026
Client Alert | 5 min read | 07.09.26
Made in the USA? Prove It: FTC Marks America's 250th with Crack Down on Domestic Origin Claims


