1. Home
  2. |Insights
  3. |Bad Estimates Support Constructive Change Without Proof of Government Negligence

Bad Estimates Support Constructive Change Without Proof of Government Negligence

Client Alert | less than 1 min read | 07.10.13

In IAP World Servs., Inc. v. Dep't of Treasury (June 20, 2013), the Civilian Board of Contract Appeals held the government liable when a maintenance contractor's service calls took longer to perform than calls in historical data furnished to prospective offerors and the government had said the historical data were a "reasonable basis" for firm-fixed-price proposals. Finding that the contractor had relied on the faulty data to price its proposal and that the contractor need not prove government negligence, the CBCA decided that the longer service calls were a constructive change to the contract and awarded the contractor its increased costs of performance.


Insights

Client Alert | 4 min read | 05.01.26

Federal Court Blocks Trump Administration Policies Restricting Wind and Solar Permitting

A coalition of regional clean energy trade associations — including RENEW Northeast, Alliance for Clean Energy New York, Southern Renewable Energy Association, and Interwest Energy Alliance — along with the Green Energy Consumers Alliance (GECA), filed suit in December 2025 against the Department of the Interior (DOI), the Bureau of Land Management, the Bureau of Ocean Energy Management, the U.S. Fish and Wildlife Service (USFWS), and the Army Corps of Engineers. The complaint alleged that five agency actions, issued in response to a series of executive orders and presidential memoranda beginning on January 20, 2025, violated the Administrative Procedure Act (APA) by arbitrarily halting or restricting federal permitting for wind and solar energy projects. Plaintiffs sought a preliminary injunction to halt enforcement of these policies while the litigation proceeds. See Renew Northeast, et al. v. U.S. Dep’t of Interior, et al., No. 25-cv-13961-DJC,  (D. Mass. Apr. 21, 2026) ECF Dkt. 89....