Bad Estimates Support Constructive Change Without Proof of Government Negligence
Client Alert | less than 1 min read | 07.10.13
In IAP World Servs., Inc. v. Dep't of Treasury (June 20, 2013), the Civilian Board of Contract Appeals held the government liable when a maintenance contractor's service calls took longer to perform than calls in historical data furnished to prospective offerors and the government had said the historical data were a "reasonable basis" for firm-fixed-price proposals. Finding that the contractor had relied on the faulty data to price its proposal and that the contractor need not prove government negligence, the CBCA decided that the longer service calls were a constructive change to the contract and awarded the contractor its increased costs of performance.
Contacts
Insights
Client Alert | 11 min read | 04.27.26
EU Pharma Package: Access Conditionalities and Shortage Measures Compromise Proposal
In our seventh alert in this EU Pharma Package Series, we provided an analysis of the increasing focus on shortages of medicinal products in the EU and the prevention and mitigation measures as proposed by the EU institutions.
Client Alert | 3 min read | 04.24.26
Client Alert | 2 min read | 04.24.26
Client Alert | 4 min read | 04.23.26
Bipartisan Coalition of State AGs Backs Federal PBM Transparency Rule


