ASBCA Dismisses "Conclusory" and "Unsupported" $100M Government Claim

Client Alert | 1 min read | 01.10.17

In Lockheed Martin Integrated Systems, Inc. (ASBCA Dec. 20, 2016), a case involving a $100 million breach of contract claim stemming from purportedly unallowable direct subcontractor costs, the Board granted Lockheed Martin’s motion to dismiss the Army’s claim "for failure to state a claim on which relief could be granted," concluding that the government had "gone forward with a claim for over $100,000,000…based on nothing more than a plainly invalid legal theory." Specifically, the Board held that final decisions based solely on an audit report’s "conclusory assertions" and "unsupported conclusions" failed to satisfy the standards required by the Board’s rules for a valid claim and that although prime contractors have a generalized responsibility to manage subcontractors, the Army failed to establish that Lockheed Martin had breached any particular contractual obligation, express or implied, and specifically that Lockheed Martin had no obligation to (1) obtain or audit incurred cost submissions from subcontractors; or (2) to retain documentation supporting prime contractor billings for longer than the contract’s "applicable records retention" period.

Insights

Client Alert | 3 min read | 07.10.26

Federal Circuit Clarifies Application of Blue & Gold: Proposal Submission Deadline, Not Award, is the Operative Time for Filing

In Utech, Inc. v. United States, No. 24-1586 (Fed. Cir. June 24, 2026), the U.S. Court of Appeals for the Federal Circuit clarified that in most cases, a pre-award protest must be filed before the proposal submission deadline to avoid the Blue & Gold waiver rule.  This decision, while nonprecedential, is in line with U.S. Government Accountability Office (GAO) precedent, which has long held that pre-award protests must be filed before the proposal submission deadline....