  3. |Bad Estimates Support Constructive Change Without Proof of Government Negligence

Bad Estimates Support Constructive Change Without Proof of Government Negligence

Client Alert | 1 min read | 07.10.13

In IAP World Servs., Inc. v. Dep't of Treasury (June 20, 2013), the Civilian Board of Contract Appeals held the government liable when a maintenance contractor's service calls took longer to perform than calls in historical data furnished to prospective offerors and the government had said the historical data were a "reasonable basis" for firm-fixed-price proposals. Finding that the contractor had relied on the faulty data to price its proposal and that the contractor need not prove government negligence, the CBCA decided that the longer service calls were a constructive change to the contract and awarded the contractor its increased costs of performance.


Insights

Client Alert | 1 min read | 04.18.24

GSA Clarifies Permissibility of Upfront Payments for Software-as-a-Service Offerings

On March 15, 2024, the General Services Administration (GSA) issued Acquisition Letter MV-2024-01 providing guidance to GSA contracting officers on the use of upfront payments for acquisitions of cloud-based Software-as-a-Service (SaaS).  Specifically, this acquisition letter clarifies that despite statutory prohibitions against the use of “advance” payments outside of narrowly-prescribed circumstances, upfront payments for SaaS licenses do not constitute an “advance” payment subject to these restrictions when made under the following conditions:...