A Rose and a Thorn: Federal Circuit Permits Contractor to Add New Claim to Pending Complaint, but Enforces Notice Provision to Bar Recovery

Client Alert | 1 min read | 02.26.15

In K-Con Building Systems Inc. v. United States, the Federal Circuit held that a contractor could amend its COFC complaint to add new, denied claims related to the appeal if the new claims either requested different remedies (e.g., additional compensation, remission of funds, non-monetary relief) or asserted legal grounds for relief that were materially different from the claims under appeal. This holding may prove helpful to contractors at the COFC who identify additional bases for recovery/remedies after filing their complaint; however, the Court also denied recovery because the contractor's two-year delay before notifying the government of the alleged "changes" failed to provide the adequate notice required by the Changes Clause, distinguishing the facts in K-Con from those in prior cases where notice provisions were not strictly enforced.

Insights

Client Alert | 1 min read | 04.18.24

GSA Clarifies Permissibility of Upfront Payments for Software-as-a-Service Offerings

On March 15, 2024, the General Services Administration (GSA) issued Acquisition Letter MV-2024-01 providing guidance to GSA contracting officers on the use of upfront payments for acquisitions of cloud-based Software-as-a-Service (SaaS).  Specifically, this acquisition letter clarifies that despite statutory prohibitions against the use of “advance” payments outside of narrowly-prescribed circumstances, upfront payments for SaaS licenses do not constitute an “advance” payment subject to these restrictions when made under the following conditions:...